Parson’s Creek Interchange

Project Statistics:

  • Location: Fort McMurray, AB
  • Value: $150 million
  • Year Completed: 2015
  • Client: Alberta Transportation
  • Our Services: Earthworks, Specialty Services, Aggregates

This project marks the largest single contract Sureway has undertaken, and the largest contract Alberta Transportation has awarded to a single contractor. The completed interchange will open up access to roughly 12,000 residents and additional businesses.

In 2014, we excavated 3,750,000 m3 of earth, and excavated another 1,750,000 m3 in 2015. Over the course of the project, we’ve placed over 1,000,000 lm of wick drains, 225,000 tonnes of road gravels, and 40,000 tonnes of asphalt. Our team also completed the bridge over Highway 63 on schedule. This project housed a mobile asphalt plant, 125 pieces of equipment, and 200 employees on site.