Enbridge Gibson Heavy Construction

Scope of Work

  • 4,000 m3 – Brownfield excavation and backfill for buried lines
  • 4,400 WIN – Shop fabrication of NPS 36” and 42” spools
  • 3,500 WIN – Field installation of NPS 36” and 42” spools
  • Pipe insulation and coating
  • Fabrication and installation of structural steel pipe rack and supports
  • Electrical installations for instrumentation & controls and heat tracing
  • Commissioning support
  • Piling

 

Project Statistics:

  • Location:Hardisty, AB
  • Duration:April 2018 – Nov 2018
  • Owner:Enbridge
  • Our Services:
    • Mechanical
    • Underground Utilities

Project Description:

Sureway was contracted by Enbridge for the construction of 36” & 42” connection piping, including all civil, mechanical, electrical and structural installations.