Scope of Work

  • 95,000 m3 – Common Excavated Earthworks For Pond
  • 800 lm – 1050mm—1800mm Storm Pipe Open Cut / Auger
  • 600 lm – Storm Pipe Through Existing Roadway
  • 75% – Excavation Trenching Required Shoring
  • 1 ls – Site Rehabilitation, Traffic Management And Landscaping
  • 1 ls – Removal And Installation Of Electrical Services & Lighting

 

Project Statistics:

  • Location:Edmonton, AB
  • Duration:May 2018 – October 2017
  • Owner:EPCOR
  • Our Services:
    • Earthworks
    • Underground Utilities

Project Description:

 Earthworks and underground utility installation to meet 1:100 year storm requirements. Work area included: residential areas, existing roadways, adjacent to a school, through natural park areas. Public consultation and notifications. Existing water & sewer remained live during new line installation. Successfully met tight timelines to complete project before school resumed. Temp Servicing for Residential Area.