Discovery Park Development

Scope of Work

  • 70,000 m2 Road Pregrade
  • 5,200 lm Sanitary Pipe w/ Auger (250mm – 375mm)
  • 4,900 lm Waterline w/ Auger (300mm – 400mm)
  • 4550 lm Storm Pipe w/ Auger (675mm – 1050mm)
  • 300 lm 200mm DR35 & 100mm DR18 PVC Forcemain
  • 1 ls Multi-Level Outfall System

 

Project Statistics:

  • Location:Nisku, AB
  • Duration:June 2017 – December 2018
  • Owner:Remington Development
  • Our Services:
    • Earthworks
    • Underground Utilities

Project Description:

 Earthworks and drainage for Remington Development Corporation – Discovery Park. (Projects within Discovery Tender: Offsite Storm, Grading, UG installation, Multi-Tenant Building Site). Whitemud Creek – multi-level outfall system installation c/w gabion baskets, class 1 riprap and erosion matting. 2.5 km of ditch widening / landscaping. 2600m of lot Services, 750m CSP Culvert and 2,000m3 of dirt excavation.