Scope of Work
- 31,200 m3 – Topsoil Stripping
- 310,000 m3 – Common Cut/Fill for Site Balance & Pond
- 2,074 lm – Storm Sewer (Onsite, Offsite, Trunks, SWMF)
- 1,560 lm – Sanitary Sewer (Onsite, Offsite, Trunks)
- 2,060 lm – Watermain (Onsite, Offsite, 150mm to 450mm dia.)
- 6,354 m2 – Road Pregrade & Asphalt Surfacing
- Sidewalks, Curbs & Gutters
- Shallow Utilitiies – Power, Gas, Communication
Project Statistics:
- Location:Edmonton, AB
- Duration:May 2018 – June 2020
- Owner:Genstar Developments
- Our Services:
- Earthworks
- Underground Utilities
Project Description:
Sureway acted as General Contractor on the 117 lot residential development for Crystallina Stage 8B & 13. Scope included Underground Deep Utility Installation (Storm, Sanitary, Water), Grading/Earthworks, Surface (Roadways) and Shallow Utility Installation. Sureway obtained all Construction Completion Certificates (CCC) for all scopes under our General Contract.