Scope of Work
- 134,000 m3 – Topsoil Stripping and Marginal Stripping
- 85,000 m3 – Common Ex from SWMF
- 80,000 m3 – Common Ex onsite
- 20,000 m2 – Subgrade Prep
- 185,000 m3 – Engineered Fill
- 4,000+ lm – Sanitary, Water, Storm Pipe
- 35 manholes, 1800mm concrete pipe and box manhole
Project Statistics:
- Location:Edmonton, AB
- Duration:Sept 2019 – Nov 2020
- Owner:Qualico
- Our Services:
- Earthworks
- Underground Utilities
Project Description:
The project involved 130,000m3 of topsoil and marginal stripping to stockpile, 170,000m3 of common ex from SWMF, 185,000 m3 of engineered fill and over 20,000m2 of subgrade completed. Over 4 km of pipe installed with 35 manholes, 1800mm dia. concrete pipe, large diameter storm and sanitary trunks, deep 525mm sanitary tie-in next to existing 450mm water valve required 8m deep slide rail trench box install, crossed shallow utilities with 1800mm storm, installed 450mm watermain. Overall a very challenging project with bad ground conditions and 40+ rain days, project was completed on schedule.