Aster Stage 2/1/4

Scope of Work

  • 134,000 m3 – Topsoil Stripping and Marginal Stripping
  • 85,000 m3 – Common Ex from SWMF
  • 80,000 m3 – Common Ex onsite
  • 20,000 m2 – Subgrade Prep
  • 185,000 m3 – Engineered Fill
  • 4,000+ lm – Sanitary, Water, Storm Pipe
  • 35 manholes, 1800mm concrete pipe and box manhole

 

Project Statistics:

  • Location:Edmonton, AB
  • Duration:Sept 2019 – Nov 2020
  • Owner:Qualico
  • Our Services:
    • Earthworks
    • Underground Utilities

Project Description:

The project involved 130,000m3 of topsoil and marginal stripping to stockpile, 170,000m3 of common ex from SWMF, 185,000 m3 of engineered fill and over 20,000m2 of subgrade completed. Over 4 km of pipe installed with 35 manholes, 1800mm dia. concrete pipe, large diameter storm and sanitary trunks, deep 525mm sanitary tie-in next to existing 450mm water valve required 8m deep slide rail trench box install, crossed shallow utilities with 1800mm storm, installed 450mm watermain. Overall a very challenging project with bad ground conditions and 40+ rain days, project was completed on schedule.