Scope of Work
- 150 lm – Sanitary Forcemain Open Cut Trenching (450mm DR11)
- 450 lm – HDD Forcemain Creek Crossing (450mm DR11)
- 1385 lm – HDD Forcemain N & S of Creek Crossing (450mm DR11)
- 1 each – Air Release Combination Valve
- 30 lm – Case Boring (Behind Burb to MH537A)
- 1 ls – Site Restoration & Landscaping
Project Statistics:
- Location:Edmonton, AB
- Duration:June 2018 – December 2018
- Owner:Qualico
- Our Services:
- Underground Utilities
Project Description:
This Project included the following: Open cut trenching of 150m of 450mm DR11 HDPE pipe. With approximately 2km of HDD trenchless along 199 street and under a the existing creek. 30m of case boring into a manhole. Also included the installation of air release combination manholes and drilling mud disposal.